Home » House Exterior » Deck & Patio » How to Replace a 6×6 Wood Deck Post – Part 2

How to Replace a 6×6 Wood Deck Post – Part 2

Bob Jackson
Last Updated on
by Bob Jackson

The sagging wood deck is pulled together with a cable winch, 2×10 deck beams reinforced with steel connectors, temporary support post set and the jack post removed. This project is continued from How to Replace a 6×6 Wood Deck Post.

How to Replace a 6×6 Wood Deck Post – Part 2

Pull the Deck Together with a Cable Winch

The Come-Along cable winch was installed How to Pull Together a Sagging Wood Deck and slightly tensioned to prevent deck movement while jacking, but I’ve waited until raising the deck to fully pull it together. Why wait? Because the deck needed to be separated from the 6×6 corner post so it would not be pulled back away.

Remember the 5/8 inch gap between the 2×10 deck beams?

Wood Deck Repair - Joists Pulling Apart
Wood Deck Repair – Joists Pulling Apart

Now I’ve cranked the winch to pull the deck together:

Sagging Wood Deck Pulled Together with Come Along Cable Winch
Sagging Wood Deck Pulled Together with Come Along Cable Winch

In the above photo, the wood is darker because I’ve poured and brushed on several coats of Copper-Green Brown Wood Preservative (10% copper naphthenate) and taking care to soak it into the old nail holes.

Next I installed two FastenMaster LedgerLok 5 inch long wood screws in a counter sunk holes so the heads will be flush with the 2×10 joist face:

Deck Repair - FastenMaster LedgerLok 5 inch Screws in Rim Joist
Deck Repair – FastenMaster LedgerLok 5 inch Screws in Rim Joist

And installed the Simpson Strong-Tie ML26Z Angle with SDS 1/4 by 2-1/2 inch structural screws on the inside corner. (The next photo was taken later in the project). I had to wait until the deck was raised and pulled together before installing the angle:

Wood Deck Repair - Simpson Strong Tie ML26Z Angle on Joists
Wood Deck Repair – Simpson Strong Tie ML26Z Angle on Joists

Install the Temporary Support Post

The full height temporary support installation steps are:

  1. Working with a helper, stand up the support post.
    The support post is set back about 18 inches from the corner 6×6 deck post for clearance to saw and jackhammer out the concrete patio slab to dig and pour a new concrete footer. The distance was determined by concrete footer dimensional drawing.
  2. Verify the support post is plumb (vertical) with a 5 foot spirit level on all sides.
  3. Lower the hydraulic bottle jack so the deck corner is resting on the 6×6 corner post and blocks.
    At this point the deck 2×10 beams should be very close to or resting on the temporary support.
  4. Lower the jack then remove the jack and jack post.
Sagging Wood Deck - Temporary Support Post
Sagging Wood Deck – Temporary Support Post

Closeup of the temporary support post and 6×6 corner post. A couple of plastic shims were wedged between the support post and 2×10 deck joists to close the gap. I’ve also installed the six remaining Simpson Strong-Tie SDS 1/4 by 2-1/2 inch structural screws in the ML26Z angle. Recall only two screws were installed while jacking to allow movement and prevent stress or binding.

Sagging Wood Deck - Temporary Support Post after Raising Deck
Sagging Wood Deck – Temporary Support Post after Raising Deck

I installed a 2×6 brace to secure the top of the support post to the deck using Simpson Strong-Tie SD #9 x 2-1/2 structural screws:

Sagging Wood Deck Repair - Temporary Support Post Fastened to Rim Joist
Sagging Wood Deck Repair – Temporary Support Post Fastened to Rim Joist

Anchor the Support Post to the Concrete Patio Slab

The base of the support post are 2×6 and 2×12 blocks fastened with the SD #9 screws for a wide stable platform. The support post will be in place for several weeks, so I anchored the base with Tapcon concrete screws to prevent movement due to accidental bumping while working with heavy equipment. I’ve drilled four holes with the hammer drill for the Tapcons:

Wood Deck Repair - Temporary Support Post Anchors
Wood Deck Repair – Temporary Support Post Anchors

Then blew the concrete dust out of the drill holes with air compressor blow gun and screwed in the Tapcons:

Wood Deck Repair - Temporary Support Post Anchored with Tapcons
Wood Deck Repair – Temporary Support Post Anchored with Tapcons

From left to right in the photo, view of the blocks on the corner 6×6 deck post, temporary support post, sister block to support the beam splice and cable winch:

Wood Deck Repair - Support Post and Cable Winch
Wood Deck Repair – Support Post and Cable Winch

And looking down from the on top of the deck:

Deck Post Replacement - Support Post Detail
Deck Post Replacement – Support Post Detail

This project is continued in How to Remove a Deck Post in a Concrete Slab.

Best,

Bob Jackson

replace 6x6 wood deck postsagging wood deck repairwood deck building code
Bob Jackson
Bob Jackson
Technology product manager by day and a prolific handyman in the evenings and over the weekends. Bob was the founder of the original Handyman How To website and that tradition continues on this site with excellent new handyman content into the future.
Leave a Reply

Your email address will not be published. Required fields are marked *